Overhaul and modernisation of a molasses transfer installation

Verum Steel fitters reading pressure gauges on an insulated pipeline

4 wks

250 m of DN200 pipeline – a week ahead of schedule

Client
A large chemical plant in Gdańsk
Scope
Overhaul, modernisation and new installations
Deadline
4 weeks – completed a week early
Scale
250 m of DN200 pipeline

01Scope of the contract

Project

Another major project for our team – a won tender for the overhaul, modernisation and construction of new molasses transfer installations at a large chemical plant in Gdańsk. The scope covered the complete replacement and extension of key infrastructure components to bring it in line with current technological and safety requirements.

02Difficulties

Challenges

The work was carried out in difficult conditions – on a pipe bridge about 10 metres above the ground, using cranes, scaffolding and cherry pickers – which required careful planning, coordination and the highest health and safety standards. From the moment we won the tender we knew the final completion date: just 4 weeks, tied to the date molasses transport to the storage tanks was due to start.

Aware of the time pressure, we approached the task professionally and organised the work in two shifts. Thanks to the team’s commitment, the contract was completed a week ahead of schedule.

03How the work was done

Execution

Fitters working on pipeline valves on the pipe bridge
  1. 01Replacement of the steam tracing pipelines made of 16Mo3 boiler steel used in high-temperature installations
  2. 02Modernisation and installation of 250 m of DN200 pipeline for molasses transport, fully maintaining the process parameters
  3. 03Replacement of instrumentation and valves with new ones
  4. 04Overhaul of the condenser and rebuild of the molasses discharge pipeline so that each line is connected to its own pump while also having bypasses that allow it to work with the other lines
  5. 05Leak and functional tests confirming correct operation of the entire system after modernisation
  6. 06Complete thermal insulation with galvanised sheet-metal cladding across the whole installation

04Outcome

Final result

4 wks

250 m of DN200 pipeline – a week ahead of schedule

The result was a modern, safe and fully functional molasses transfer installation, adapted to the current needs of the plant. Delivery on time – and a week ahead of schedule – proved the effectiveness of our approach and the high level of organisation and commitment of the team. The project strengthened our position as a reliable contractor for complex modernisations of process installations, including under heavy time pressure and difficult logistics.